TriCare Stafford Construction Update

The TriCare Aged Care Facility at Stafford is currently on program for completion in late 2017.

 

Construction summary


The roof lining is on and the scaffold is still erected, with external cladding trades completing the stonework, CFC, metal soffits and
Trespa cladding.
90% of external rendering is complete and painted, with just some minor areas of slab to go.
Building glazing is in place and the structure is sufficiently watertight for the interior lining trades, with 70% of ground level and 20% of
level 1 now lined.
100% of the modular ensuites have been placed and plugged into services.
Painting has begun in the resident rooms on the ground floor and level 1. A sample resident room has been completed and signed off
by our client, thus other room fitouts are underway including placement of joinery.
Interesting fact – To streamline construction each room is modular and features an ensuite that was manufactured in a
factory off site.

PDT Architects 31st May 2017